Currently we have a PRTG Cluster containing 1 Primary Node and 1 Secondary Node.
Now we want to Reinstall the Server hosting the Secondary Node.
What are the exact Steps to Migrate this Secondary Node to the new Server?
Article Comments
Attention: This article is a record of a conversation with the Paessler support team. The information in this conversation is not updated to preserve the historical record. As a result, some of the information or recommendations in this conversation might be out of date.
Hello,
So joining the Cluster with a Node containing the same Name as the old one is no Problem? I dont have to delete it before i "rejoin" the Cluster?
Jul, 2011 - Permalink
Dear Andreas, that should be no problem, as a cluster can have up to 5 nodes. It's only recommended to shut down the old failover node, as otherwise the new one might only start in freeware mode due to license reasons.
Jul, 2011 - Permalink
Dear Andreas,
we would recommend the following steps:
Jul, 2011 - Permalink