The one time maintenance window option in the system today has been a big help for working within Change Control windows, but I have a need for pre-scheduling reoccuring maintenance.

Several of our external vendors have their own maintenance times, which reoccur at the same date/time each week, and I'd like to be able to pre-set that in PRTG. Is there a way to do this? If not, can it be added to a futures list?

Would be a big help. Thanks!


Article Comments

Could you just create a normal schedule for this?


Apr, 2014 - Permalink

Schedules would be also my suggestion if the maintenance is re-occuring regularly at the same time each week. You can define inactive time slots with period definitions in the schedules settings of an account.

See PRTG Manual: Account Settings—Schedules


Apr, 2014 - Permalink

Makes sense! Thank you both for your replies.


Apr, 2014 - Permalink