We currently have a prtg cluster consisting of one master node and one failover node located in two separate buildings. We also have several remote probes in other buildings. The current setup is running on windows 7 64bit PCs.
What would be the best approach to migrate the above setup to Windows Server 2012R2 Virtual Machines with minimum downtime and minimum monitoring data loss.
Article Comments
Remember to prepare the remote probes as well - they're gonna need the new IP address of the core server. Given that you intend to change it :) Thanks thomas for the small walkthrough! I fixed your post layout to make it a bit more readable - hope that's okay :)
You could also take a look at our migration guide to make sure you don't miss anything.
Sep, 2015 - Permalink
Hi Oreilldyr
Hmm Maybe PRTG Support has a better way, but mine would be:
Depending how good you are prepared, and it works that way, I would say downtime > 1minute (depends on the size of the DB to copy)
regards Thomas